Xcel Energy plans to bury more than seven miles of power lines at Palo Duro Canyon, a move that will place a portion of the electrical infrastructure at one of the Texas Panhandle’s most recognizable natural landmarks underground.

The project comes amid growing concerns about wildfire prevention and the vulnerability of overhead electrical infrastructure to extreme weather conditions across the Texas Panhandle.

According to Xcel Energy, the project will involve the installation of 7.31 miles of underground distribution lines and the removal of more than six miles of overhead power lines. Construction will take place in both Randall and Armstrong counties and will be divided into more than 10 phases.

Work includes electrical infrastructure within Palo Duro Canyon State Park and along the canyon rim, utilizing Texas Department of Transportation right-of-way.

The project is intended to reduce the chances of electrical equipment igniting wildfires while preserving the natural beauty of the state park.

Palo Duro Canyon State Park Superintendent David Fischer expressed support for the project, pointing to its safety and conservation benefits.

Xcel Energy's local Canyon crews are handling the utility work alongside contractor Driver Directional. Before construction began, archaeological and geological studies were conducted under permits issued by the Texas Parks and Wildlife Department.

Those precautions are particularly important given the canyon's historical and environmental significance.

Archaeological evidence indicates that humans have inhabited Palo Duro Canyon for approximately 12,000 years. The canyon also contains geological formations dating back hundreds of millions of years and provides habitat for numerous wildlife species.

The state park opened in 1934, with much of its original infrastructure constructed by the Civilian Conservation Corps. Preserving the canyon's natural appearance was an important consideration during the park's original development.

Today, Palo Duro Canyon remains a major outdoor recreation destination for Panhandle residents and tourists. Visitors can explore more than 30 miles of trails, stay in historic cabins, camp overnight or attend summer performances of the TEXAS Outdoor Musical.

Removing overhead electrical lines could help preserve the scenic landscape that draws visitors to the park.

Part of a broader wildfire prevention effort

The Palo Duro Canyon project is not the only effort by Xcel Energy to move electrical infrastructure underground in the Texas Panhandle.

The company has also identified underground power line projects in the Timber Creek Canyon, River Falls, Sunday Canyon and Palo Duro Club areas.

Where overhead infrastructure remains necessary, Xcel Energy is utilizing other wildfire mitigation strategies, including equipment upgrades, protective electrical devices and infrastructure inspections.

Underground power lines have the advantage of being less exposed to strong winds and contact with surrounding vegetation, both of which can contribute to electrical equipment-related wildfire hazards.

However, burying electrical infrastructure does not eliminate every risk associated with delivering electricity. Underground equipment can still experience failures, and locating and repairing damaged buried cables can present additional challenges for utility crews.

A total construction cost and anticipated completion date for the Palo Duro Canyon project were not included in Wednesday's reporting.

Once completed, the project will remove miles of visible electrical infrastructure from portions of the canyon while maintaining electrical service. For Palo Duro Canyon State Park, the effort represents an opportunity to address wildfire safety concerns while protecting one of the Texas Panhandle's most treasured natural resources.